So you’ve chosen your building partners (builder, architect, contractor or an nbn trained supplier) and you have your planning and building permits. Now is the perfect time to start planning for the nbn broadband access network.
If you are building a small development, such as a sub-dividing a lot into two residential units, please allow a minimum of three months’ notice before the required service date to help ensure the network can be connected in time for new residents. For all other developments, allow a minimum of six months’ notice before an active nbn connection is required. Keep in mind, all nbn infrastructure within your property boundary needs to be installed following our guidelines or you may have to remediate it later if it is not built to our standards.
Please note: nbn will endeavour to achieve these timeframes, but cannot guarantee these timeframes in all cases.